Oklo's Meta Deal Calls For a 1.2-Gigawatt Reactor in Ohio. Here's When It's Slated to Come Online.
Oklo announced an agreement with Meta to develop a 1.2-gigawatt nuclear facility in south central Ohio to power Meta's data centers. Pre-construction is scheduled for 2027 with general construction beginning in late 2028 or 2029, with the first phase expected online around 2030. However, the unproven small modular reactor (SMR) technology makes a 2030 timeline unlikely, with a later date being more plausible. Oklo's stock is down 45% this year as investors remain cautious about the company's business model and SMR viability.